Task |
Responsible party |
Days to Complete |
|
|
|
Identify property(s) |
CEO of Parikh Foundation |
30 |
Secure approvals |
Director of Construction |
30 |
Obtain 3 quotes on site prep |
Director of Construction |
14 |
Obtain 3 quotes for Greenhouse |
Arthur & Friends |
7 |
Obtain 3 quotes for Hydro |
Arthur & Friends |
7 |
Develop Budget first 12 months |
Arthur & Friends |
14 |
Post Jobs |
Arthur & Friends |
1 |
Interview applications |
Arthur & Friends |
7 |
Conduct Food assessment |
Arthur & Friends |
7 |
Secure agreements with restaurants |
Project Director |
7 |
Order seeds and plan production |
Project Director |
1 |
Order seeds and plan production |
Project Director |
1 |
Meet with collabotators |
Arthur & Friends |
1 |
Identify first 10 Friends to participate |
Project Director |
14 |
Select vendors (i.e. Greenhouse, etc.) |
Project Director |
1 |
Create POs |
Arthur & Friends |
1 |
Pour Concrete Slab |
Vendor |
5 |
Hook up electric, Gas, water |
Vendor |
5 |
Greenhouse construction |
Vendor |
14 |
Install Hydroponics |
A & F, G.H. Mgr., volunteers |
14 |
Train manager and staff |
Arthur & Friends |
7 |
Begin first group of Friends |
Training Mgr. |
1 |
First Seeding |
Arthur & Friends & staff |
32 |
First Harvest |
|
|