| Task | Responsible party | Days to Complete |
| Identify property(s) | CEO of Parikh Foundation | 30 |
| Secure approvals | Director of Construction | 30 |
| Obtain 3 quotes on site prep | Director of Construction | 14 |
| Obtain 3 quotes for Greenhouse | Arthur & Friends | 7 |
| Obtain 3 quotes for Hydro | Arthur & Friends | 7 |
| Develop Budget first 12 months | Arthur & Friends | 14 |
| Post Jobs | Arthur & Friends | 1 |
| Interview applications | Arthur & Friends | 7 |
| Conduct Food assessment | Arthur & Friends | 7 |
| Secure agreements with restaurants | Project Director | 7 |
| Order seeds and plan production | Project Director | 1 |
| Order seeds and plan production | Project Director | 1 |
| Meet with collabotators | Arthur & Friends | 1 |
| Identify first 10 Friends to participate | Project Director | 14 |
| Select vendors (i.e. Greenhouse, etc.) | Project Director | 1 |
| Create POs | Arthur & Friends | 1 |
| Pour Concrete Slab | Vendor | 5 |
| Hook up electric, Gas, water | Vendor | 5 |
| Greenhouse construction | Vendor | 14 |
| Install Hydroponics | A & F, G.H. Mgr., volunteers | 14 |
| Train manager and staff | Arthur & Friends | 7 |
| Begin first group of Friends | Training Mgr. | 1 |
| First Seeding | Arthur & Friends & staff | 32 |
| First Harvest |